A considered, market-ready speculative suite designed to stand out in the Abbotsford leasing market.
Dear Aaron,
Thank you for the opportunity to present our proposal for the speculative suite fitout at Ground Floor, 452 Johnston Street, Abbotsford.
Concept is committed to working alongside Ork Designs to ensure clarity, precision, and long-term value at every stage of this project. We understand the importance of transforming underutilised flex space into a compelling, market-ready offering that positions Abacus strongly within the Abbotsford leasing market.
Our approach centres on retaining the original design intent while providing well-considered cost saving options that strengthen Abacus’s incentive offerings on future leasing deals. Every recommendation we make is grounded in practical delivery expertise, ensuring design quality is never compromised in the pursuit of efficiency.
With a structured, transparent process and a team that controls programme from start to finish, we are confident in delivering a high-quality product, on time, and within a competitive budget. We look forward to a strong collaboration that delivers a positive outcome for all stakeholders.
In response to the Neoscape Principal’s Project Requirements (PPR) dated 11 March 2026, Concept acknowledges the following scope of work for Ground Floor, 452 Johnston Street, Abbotsford.
Light refurbishment to convert an existing flex (coworking-type) space into a single speculative suite. Includes demolition of several flex rooms to create open workspace and reconfiguration of the entry with a new waiting area.
Reconfiguration of the main entry point, including shifting the entry door and creation of a new waiting area to establish a professional first impression for prospective tenants.
A mix of new and reallocated furniture within the asset, coordinated with the Ork Designs furniture schedule to deliver a market-ready workspace that supports flexible tenancy configurations.
Separate to the spec suite scope, minor modifications to convert 2 existing meeting rooms into a Building Management Office (BMO) and office for a small flex tenant. This work is programmed first to enable tenant relocation.
Cost Option (Below the Line)
Ceiling/lid to the 16-person boardroom and associated services, priced separately for Abacus’s consideration.
Design: Ork · Services: Aston · RBS: McKenzie · Project Manager: Neoscape
Contract Document Register — Priced On
This proposal is a fixed-price lump sum based on the following documents issued under Neoscape Tender Addendum 06 (11 March 2026). All pricing is inclusive of the scope described within these documents.
| Author | Discipline | Document | Rev |
|---|---|---|---|
| Ork | Architect | Construction Package | C3 |
| Ork | Architect | Finishes Schedule | C2 |
| Ork | Architect | Furniture Schedule | C2 |
| Ork | Architect | General Arrangement Plan | C2 |
| Ork | Architect | Reflected Ceiling Plan (RCP) | – |
| Ork | Architect | Sketch Plan – Option 1 | – |
| Aston | Services | Electrical – E00, E10, E20, ESPEC | B–D |
| Aston | Services | Fire – F00, F10, FSPEC | B–D |
| Aston | Services | Mechanical – M00, M01, M10, MSPEC | C–D |
| Neoscape | Project Manager | Principal’s Project Requirements (PPR) | 1 |
| Neoscape | Project Manager | Tender Addendum 06 | – |
| McKenzie | RBS | Building Surveyor Checklist | 01 |
We listened carefully during our briefing. Here is what we understand matters most to Abacus on this project.
Transform underutilised flex space into a compelling speculative suite market offering to the Abbotsford area. The end product must be a leading proposition that attracts quality tenants and supports strong leasing outcomes.
Ensure that design remains in line with a competitive budget so that design intent is retained throughout the project. Every dollar invested must contribute to the quality and appeal of the finished space.
Concept to provide cost saving options that reduce costs where possible, boosting incentive offerings on leasing deals without diluting the Ork Designs intent.
Deliver the project efficiently and bring it to market as soon as possible, ensuring top-level workmanship and a quality product throughout.
For over 48 years, Concept Commercial Interiors has delivered exceptional workplace fitouts across Australia. With 240+ in-house trades and a team of 65+, we offer the certainty, quality, and speed that traditional procurement simply cannot match.
Concept delivered our project on time, on budget, and to a standard that exceeded our expectations. Their in-house team made the entire process seamless from start to finish.
9.4/10 Average Customer Satisfaction
A lifetime defect guarantee on all work we deliver. We stand behind the quality of every fitout, giving you confidence long after handover.
One fixed price for the entire project. No variations, no surprises, no blowouts. You know exactly what you are investing from day one.
98% of our projects are delivered on time or early, thanks to 240+ in-house trades. No subcontractor delays, no excuses.
A complete space plan and indicative budget within 48 hours of your brief. Speed of response matched with depth of analysis.
Our structured process ensures clarity at every stage, from initial brief through to handover and beyond.
Detailed review of the Ork Designs documentation, site conditions, and project objectives. We align on scope, budget parameters, and programme expectations.
Working alongside Ork Designs to refine specifications, identify value engineering opportunities, and confirm material selections that protect design intent.
Procurement, trade scheduling, and site preparation. Our in-house team locks in programme certainty before a single tool hits site.
240+ in-house trades deliver the fitout with precision and accountability. Weekly progress reporting keeps all stakeholders informed throughout.
Thorough quality inspection, defect-free handover, and a market-ready suite prepared for leasing activity and tenant inspections.
A handpicked team of specialists assigned exclusively to deliver the 452 Johnston Street project for Abacus.
Beyond delivery, Concept actively supports the leasing process to ensure spec suites attract quality tenants and achieve strong commercial outcomes.
Every detail is considered through a leasing lens. The finished suite is designed to photograph well, inspect well, and compete strongly in the Abbotsford market.
Specifications are selected to appeal to the broadest range of tenants while maintaining a premium positioning that supports asking rents.
Cost saving options are identified specifically to boost the incentive pool available for leasing deals, maximising return on the landlord investment.
Our in-house delivery model compresses programme timelines, bringing the suite to market faster and reducing holding costs for Abacus.
The following is Concept’s fully priced fixed-price lump sum offer, based on the contract documents listed under the Neoscape Tender Addendum 06 document register. No provisional sums or contingencies — this is the price to deliver.
Reference L111 · Issued 23 March 2026 · Valid 14 days
| # | Trade Package | Amount (ex GST) |
|---|---|---|
| 01 | Building Permit Drawings, surveying, application, lodgement, council fees, final inspection certification, asset protection insurance |
$5,660.00 |
| 02 | Ceilings, Partitions & Doors A-Type & B-Type walls, 300mm bulkhead to boardroom, aluminium glass sliding doors with D-pull handles, 32m² solid plaster ceiling |
$27,307.53 |
| 03 | Demolition Remove plaster & glass partitions, doors, fixed joinery, carpet removal & stacking for relaying |
$21,816.09 |
| 04 | Electrical Services Disconnect & make safe, socket outlets, Cat 6a data points, patch panel, RCBO, COES, testing & commissioning |
$23,660.76 |
| 05 | Fire & Life Safety Devices 4 new sprinkler heads (rough in & fit off), 1 speaker, 1 smoke detector |
$7,865.00 |
| 06 | Floor Finishes Install FF1 tiles, relocate EX2 tiles from FOH meeting rooms, black PVC dim strip to polished concrete |
$2,689.50 |
| 07 | Floor Leveling & Grinding Slab grinding where necessary |
$1,165.90 |
| 08 | Furniture Re-Assembly Remove items for build works, reattend to relocate & position furniture per proposed plans |
$13,535.00 |
| 09 | Lighting PL1 – Home of Lights Laverd Collection Bar Light, relocate 2 sensors |
$8,318.33 |
| 10 | Loose Furniture Co-op tables (2400W & 2100W D-End), Sparki power boxes, umbilicals, Cosmopolitan round table, installation |
$19,843.73 |
| 11 | Mechanical Services NEBB certified works, boardroom PAC, open office water cooled PAC, plumber labour, BMS (Alerton), ductwork & grills |
$156,737.50 |
| 12 | Painting & Decorating Patch & paint all necessary walls, two coats Dulux |
$10,159.56 |
| 13 | Preliminaries Coordination, surveying, site establishment, OH&S, insurances, temporary services, amenities, cleaning, plant hire |
$28,182.01 |
| Total (ex GST) | $326,940.91 | |
| GST (10%) | $32,694.09 | |
| Total (inc GST) | $359,635.00 |
| # | Description | Amount (ex GST) |
|---|---|---|
| 29.1 | Supply & install 2 off aluminium glass swing doors to suit existing mullion positions | $25,125.00 |
| 29.2 | Extend boardroom solid partition to slab above | $5,250.00 |
| 29.3 | Engineered post structure to slab above | $5,700.00 |
| 29.4 | Lighting – Plug Base installation | $1,800.00 |
| 29.5 | Lighting – 1 Gang Iconic Switch supply & install | $4,590.00 |
| 29.6 | Supply of DL1 – TBC PC Sum | $1,875.00 |
| 29.7 | Open Office Water Cooled PAC-G.1.2 – ductwork, grills & installation hardware | $27,300.00 |
| 29.8 | BMS (Alerton) – Open Office Water Cooled PAC 1 x PAC-G.1.2 | $12,000.00 |
| 29.9 | Plumber Labour – Open Office Water Cooled PAC-G.1.2 | $18,375.00 |
| 29.10 | BMS (Alerton) – 3 x Energy Meters (power meters by electrical contractor) | $6,237.50 |
| Options Total (ex GST) | $108,252.50 |
General Exclusions
All prices in Australian dollars. Fixed-price lump sum — no provisional sums. Valid 14 days from issue. Ref: AFS-L111.
A 45-day delivery programme from commencement through to CFI handover, with BMO modification works sequenced first to enable tenant relocation before commencing the spec suite conversion.
| # | Task | Start | End | Days |
|---|---|---|---|---|
| Pre-Construction | 27/03 | 25/05 | 42 | |
| 1.1 | Design documentation finalised | 27/03 | 02/04 | 5 |
| 1.2 | Construction drawings completed | 03/04 | 09/04 | 5 |
| 1.3 | Client approval & Owners’ Consent | 13/04 | 13/04 | 1 |
| 1.4 | LOA signed | 14/04 | 14/04 | 1 |
| 1.5 | Building permit obtained | 15/04 | 15/04 | 1 |
| 1.6 | Contract signed | 15/04 | 17/04 | 3 |
| 1.7 | Procurement | 15/04 | 21/04 | 5 |
| Construction | 16/04 | 25/05 | 28 | |
| 1.8.1 | Site establishment | 16/04 | 16/04 | 1 |
| 1.8.2 | Mechanical pre-read | 16/04 | 16/04 | 1 |
| 1.8.3 | Isolations & make safe | 17/04 | 17/04 | 1 |
| 1.8.4 | Modification to Building Management Office | 17/04 | 22/04 | 4 |
| 1.8.5 | Demolition | 23/04 | 29/04 | 5 |
| 1.8.6 | Set out / Framing | 30/04 | 04/05 | 3 |
| 1.8.7 | Electrical rough-in | 04/05 | 06/05 | 3 |
| 1.8.8 | Mechanical rough-in | 05/05 | 07/05 | 3 |
| 1.8.9 | Plumbing rough-in | 06/05 | 06/05 | 1 |
| 1.8.10 | Sheet walls | 07/05 | 11/05 | 3 |
| 1.8.11 | Painting | 12/05 | 13/05 | 2 |
| 1.8.12 | Flooring installation | 14/05 | 18/05 | 3 |
| 1.8.13 | Acoustic panel installation | 19/05 | 19/05 | 1 |
| 1.8.14 | Furniture delivery | 20/05 | 20/05 | 1 |
| 1.8.15 | Furniture installation & placement | 21/05 | 21/05 | 1 |
| 1.8.16 | Services fit-off & commissioning | 22/05 | 25/05 | 2 |
| Completion | 26/05 | 28/05 | 3 | |
| 1.2 | Final clean | 26/05 | 26/05 | 1 |
| 1.3 | Building Surveyor inspection | 27/05 | 27/05 | 1 |
| 1.4 | CFI — Handover Date | 28 May 2026 | ||
Programme considers BMO modification works first to enable tenant relocation before commencing spec suite conversion, as required by the PPR.
We are ready to move forward on 452 Johnston Street. Reach out to your dedicated Concept team to discuss next steps.